Size a 12 V off-grid bank from load, autonomy days and depth of discharge, then check how you wire it. A repeatable method for system builders.

Off-grid battery banks rarely fail because the cells were bad. They fail because the bank was sized from the panel that happened to be available, or from the capacity a competitor quoted, instead of from the load and the number of sunless days the site has to survive. This guide walks through the sizing sequence in the order it should be done, using a 12 V lead-acid bank as the example, and finishes with the wiring checks that decide whether the bank ages evenly or dies young.
Step 1 - Start with the load, not the panel
Everything downstream depends on how much energy the site consumes in a day, so list the loads first: what runs, for how many hours, and how many watts each item draws. Multiply watts by hours for each load and add them up for the daily watt-hour total. Lamp schedules, pump duty cycles and the standby draw of inverters and controllers belong in this list - standby is the line item most often forgotten, and on small systems it can be a meaningful share of the night.
Where loads are intermittent, agree with the end user what 'typical' means before you quote. A pump that runs two hours in summer and six in the wet season changes the bank size substantially, and that assumption belongs in writing.
Step 2 - Convert daily watt-hours into amp-hours
Lead-acid capacity is quoted in amp-hours, so convert: divide the daily watt-hours by the system voltage. On a 12 V bank, a 1200 Wh daily load asks for 100 Ah per day before any allowance for autonomy or losses. This single conversion is where most off-grid quotations go wrong, because it is often skipped and replaced by a round number copied from an older job.
Two corrections belong in the same calculation. First, usable capacity is not the same as nameplate capacity: the deeper you discharge a lead-acid cell every night, the fewer cycles it delivers, so the Ah figure you calculated has to be divided by the depth of discharge you are prepared to accept. Second, the published amp-hour rating assumes a slow discharge rate (commonly quoted at the 20-hour rate); draw the same bank harder and the effective capacity falls. Both effects push the required bank size upward, and ignoring either one produces a system that meters perfectly on day one and sags by the second season.
Step 3 - Choose autonomy days for the worst season
Autonomy is how many consecutive days the bank must carry the load with little or no useful charge. It is a commercial decision as much as a technical one: more autonomy means a bigger bank and a bigger cost, less autonomy means either a generator, a load-shedding strategy, or unhappy customers. Ask what actually happens at the site when the sun does not appear - that answer sets the number. Size the panel to recharge afterwards from the sun hours available in the weakest month, not the annual average, or the bank will spend its life in a partial state of charge.
Step 4 - Depth of discharge decides how long it lasts
Depth of discharge is the share of capacity taken out before recharging. It is the strongest lever on service life that you control at specification stage: routinely taking a deep bite out of a lead-acid bank shortens its cycle life, while a shallower cycle pattern costs more up front and lasts considerably longer. The right answer depends on what the customer values - lowest first cost per amp-hour, or lowest cost per year of service - and that trade-off should be stated explicitly in the quotation rather than left implicit.
Temperature compounds this. Cold reduces the capacity a lead-acid bank can actually deliver, which matters on unheated sites; heat accelerates ageing, which matters in poorly ventilated enclosures. Ask where the bank will live before you finalise the capacity, and give the enclosure some thought - it is the cheapest life-extension available.
Step 5 - Series, parallel and how the wiring changes the answer
Battery blocks are wired in series to raise voltage and in parallel to raise amp-hours, so a 12 V bank is built by paralleling blocks or by using larger single units. Whichever you choose, two rules protect the investment: keep every block in the string the same type, capacity and age, and keep the cabling symmetrical so all blocks see the same round-trip resistance. Mixing ages or capacities in one parallel string is a reliable way to shorten the life of the whole bank, because the weakest block drags the rest down.
Then check the practical details that decide whether the bank can be serviced: fuse or breaker protection per string, cable sized for the actual current with the run length accounted for, ventilation for gassing during charging, and a location where somebody can inspect terminals without dismantling the installation.
Sizing checklist
Item | What to confirm | Why it changes the bank size |
Daily load in watt-hours | Every load, its hours, plus inverter standby | The starting point for every calculation |
System voltage | 12 V, or a higher bus with series strings | Converts watt-hours into amp-hours |
Autonomy days | Consecutive sunless days to cover | Multiplies the daily amp-hour figure directly |
Depth of discharge | Agreed maximum daily discharge | Decides usable capacity and cycle life |
Discharge rate | Peak current against the rated rate | High rates reduce effective capacity |
Ambient temperature | Coldest and hottest months at the site | Cold cuts delivered capacity, heat cuts life |
Protection and access | Fusing, cable runs, ventilation, inspection access | Determines whether the bank can be serviced safely |
The three mistakes that kill banks early
First, sizing from the panel rather than the load - a generous array hides an undersized bank for a few months, then fails in the first bad week. Second, ignoring depth of discharge: a bank that is technically large enough but discharged deeply every night will not reach the cycle life quoted in the datasheet. Third, mixing blocks of different ages or capacities in one string, or wiring them asymmetrically, which ages individual blocks far faster than the rest. All three are specification decisions, not product defects, and all three are avoidable with the checklist above.
What to send your supplier
Send the daily watt-hour load, the system voltage, the autonomy days, the agreed depth of discharge, the ambient temperature range and the installation constraints. With those six, a supplier can propose a block configuration and flag anything in the brief that will not work - before the container ships rather than after commissioning.
Next step
Our lead-acid range covers the capacities most off-grid projects are built around, including 12 V blocks for solar storage duty. Send us your load list, autonomy requirement and site temperature range and we will size the bank against your brief, with the configuration and protection items called out separately so nothing arrives missing.